Stand Construction Update - 16th April 2010
East Stand
The concrete floor pads for the concession areas are being laid. The first and second floors have now been installed and screeded. The polycarbonate roof covering the terracing is nearing completion. Steel supports for the gable end glazing at the pavilion end are in position.
Along the upper rows of the seating deck the seat brackets have been positioned although the seats themselves will not start being installed until later this month.
Electrical cabling beneath the terracing is being installed.
West Stand
The concrete floor pads for the concession areas have started to be laid. The metal deck that forms the base of the first and second floors has been installed with the screed being laid next week. Installation of the polycarbonate roof above the terracing section is progressing well and should be completed next week.
Photo Gallery

- LatestPlease install the latest Flash media player in order to view this content.
- View all videos
-
Next Match
-
Last Match

An innovative organisation providing everyone involved in recreational cricket a safe environment...